The project was launched with the stated objective of an overall improvement in the quality of state Institutions by way of infrastructure,additional capacity building ,creation of an enabling atmosphere in the higher educational institutions for research and innovations amongst others. Acharya Prafulla Chandra College received approval for a grant of Rs. 2 crore under RUSA-2.0 Project in 2018.
Details of fund received
Sl No | Letter no. and date | Amount | |||
---|---|---|---|---|---|
(i) (ii) |
196-EH/RUSA-2.0/240/18/Comp-9 dated 21.08.2018 (iv)-EH/RUSA-240/RUSA-2.0/Comp-9 Dated 15/05/2020 |
|
|||
Rs. 1,00,00,000 | (1 Crore ) | 50,00,000 | (50 Lakhs) |
The fund breakup and utilization (as on 1.09.2023) under the different heads were as follows
Sl.No. |
Item |
Payment Made (Rs) | Amount allotted as per DPR(Rs) | Remarks |
---|---|---|---|---|
1 | *New Construction | 1,00,00,000.00 | 12488150.00 | Completed and inaugurated on 30.03.2022 with actual Total expenditure of Rs.1,14,79,535.00 |
2 (i) | *Renovation-Toilets and Library | 1129107.00 | 1272008.00 | Completed. |
(ii) | Renovation of Corridors and staircase | 20,25,565.00 | E-tenders to be floated on availability of fund | |
3 | Campus development | |||
(i) | Solar Power plant | 21,13,000 | E-tenders to be floated on availability of fund | |
(ii) |
Water treatment plant |
11,51,680 | E-tenders to be floated on availability of fund | |
4 | Procurement of New Items | |||
(i) | Sports Equipment | 417996.00 | 516720.00 | All Orders completed. |
(ii) | Computers & peripherals | 9,57,938 | 1213707.00 | E-tender for remaining items to be float on receipt of funds |
(iii) | Laboratory Equipments | 11,45,753 | 1246165.00 | Completed |
(iv) | Books | 638017.00 | 745000.00 | Orders placed, payments to be made once all the items are received. |
(v) | E-Resource I (e-books) | 2,03,978.00 | 608700.00 | Completed |
(vi) | E-Resource II (e-journals) | 4,61,156.00 | Completed | |
Total | 1,49,53,945.00 | |||
Balance | 46,055.00 |